Skip to content

Case Study

Screenshot 2025-08-05 at 6.47.22 AM

Thoresby Vale

Overview: Ongoing delivery of 220 units for Barratt & David Wilson Homes, built on a former colliery site. Mix of housing association and private sale plots.

Key challenges: Complex foundations (deep trench, vibro piling, steel ring beam) and mid-project design changes due to Part L regulation updates.

Our approach and outcome: Worked closely with the client to redesign and switch to block & beam floor systems. Ensured full NHQB compliance without slowing site progress. Currently contributing to another 3 NHBC Quality Awards with results expected late 2025.

Case Study

default

The Meadows

Overview: 124 timber-framed units on a sulphate-heavy site for Barratt Homes.

Key challenges: Poor ground conditions, tanking requirements, and the need for Spantherm floor systems to suit timber frame construction.

Our approach and outcome: Delivered multiple foundation types, managed Heaviseal tanking works, and ensured all NHQB documentation and photos were provided to spec.

Case Study

Screenshot 2025-08-05 at 6.48.00 AM

Lancaster Grove

Overview: 58 David Wilson Homes plots next to The Meadows site, on an extremely tight site footprint.

Key challenges: Tight access, deep foundations, high sulphate levels, and strict site management requirements.

Our approach and outcome: Delivered a full foundation and muck management package. All works Part L and NHQB compliant from the start, including block & beam floors and screed finishes.

Case Study

default

Roman Ridge

Overview: A premium development of 13 luxury homes delivered in partnership with Ardent Homes & Designs, featuring traditional block & beam construction and a full R&S package.

Key challenges: Located in a conservation area surrounded by TPOs, the project demanded sensitive material choices and eco-conscious design, including a sustainable permeable paving system.

Our approach and outcome: We worked closely with stakeholders to maintain the site’s integrity while delivering a full groundworks and bespoke landscaping package, showcasing the full breadth of our capabilities.

Case Study

Screenshot 2025-08-05 at 6.48.47 AM

Manor Farm

Overview: 6-phase, 1,000-home development completed over 14 years for Barratt & David Wilson Homes.

Key challenges: Mixed ground conditions and long-term consistency in delivery.

Our approach and outcome: Delivered trench foundations, vibro piles, and suspended slabs. Helped the site win 17 NHBC Quality Awards and a Seal of Excellence. Also supported nomination to the Barratt Champions League.

Case Study

Kings Court

Kings Court

Overview: David Wilson Homes site adjoining Manor Farm with a higher-spec housing range.

Key challenges: Larger homes with faster handover targets, and MoD plot allocation.

What we did: Delivered a combination of trench and vibro piled foundations. Met all MoD handover requirements on time and helped secure additional NHBC awards during the build.

Case Study

saxilby

Saxilby Heights

Overview: Rescue project taken over mid-build from a previous contractor on behalf of Taylor Wimpey.

Key challenges: Inherited disorganised, unsafe site with partial works and missing documentation.

Our approach and outcome: Reorganised and secured the site, assessed existing work with Taylor Wimpey and utilities, and completed all plot works, swales, and SUDS pond. Delivered road and footpath remedials for adoption.

Case Study

tennyson fields

Tennyson Fields, Louth

Overview: 100-plot hillside development in Louth for Lovell Homes.

Key challenges: Severe water management issues and changing site conditions due to weather.

Our approach and outcome: Amended the programme to capitalise on dry weather, installed boundary drainage, and diverted water into the site’s SUDS system. Regained full programme sequence without delay.

Case Study

Ingelby

Ingelby View

Overview: 132 residential and housing association plots showcasing sustainable drainage design.

Key challenges: High water table, tight drainage requirements, and unique planning obligations.

Our approach and outcome: Installed deep trench foundations and Spantherm floors. Delivered a full SUDS system and completed a council graveyard extension and commemorative Fallen Garden tribute.

Case Study

Screenshot 2025-07-29 at 10.04.17 AM

The Oaks

Overview: 35-plot Lovell Homes site on a constrained, previously developed site.

Key challenges: Incorrect utility drawings, broken land drains, live gas mains, and limited working hours due to neighbours.

Our approach and outcome: Resolved multiple live site issues through clear communication with all stakeholders. Completed all groundworks ahead of programme despite restrictions.

Case Study

Newton Grange

Newton Grange

Overview: 99 plots on a former railway yard for David Wilson Homes.

Key challenges: Poor ground, concrete piles, environmental protection for local newt population.

Our approach and outcome: Installed complex ring beam foundations over pile caps, managed clay heave protection, and maintained perimeter newt barriers with full compliance during Natural England inspections.

Case Study

orchards

The Orchards

Overview: 9 raft foundation bungalows on a tight cul-de-sac site.

Key challenges:
Poor access, restrictive working hours, and faulty original designs.

Our approach and outcome:
Worked with engineers to redesign foundations and storm systems. Took control of foul connections with minimal disruption. Installed a custom Hydrobreak storm system into SUDS pond.

Our Accreditations and Those We Are Proud to Work Alongside

Precision groundworks, delivered to the highest standard

Site Links

Company information

Company # 13235343
VAT GB 407 9974 52

Contact information